Scheduled Construction Activities
Week of November 30, 2015

rdbarrierCALTRANS work on Tunnel Road

Detailed information pertaining to construction projects and related activities within the city.

Subscribe to this page to receive e-mail notification when new information is posted

  1. Sanitary Sewer Rehabilitation Projects

    1. Sanitary Sewer Rehabilitation
      Panoramic Way Area Phase III - Panoramic Way (from 208 Panoramic Way to 365 Panoramic Way), Panoramic Place, Mosswood Road (above Arden Path) backline, and the backline on 158 Panoramic Way and 160 Panoramic Way
      Pacific Trenchless, Inc.
      Project Notice and Map (.pdf)

      Work in Panoramic Way area has been completed. No scheduled construction activity.

    2. Sanitary Sewer Rehabilitation
      Rugby, Vermont, Vassar, Boynton backline, Florida, Santa Barbara, La Loma Path, Shattuck, Oxford, Monterey, Masonic, San Pablo, Cornell, Cedar, 7th, 8th, 9th, 10th, and Regent
      Mosto Construction
      Project Notice and Map (.pdf)

      Rehabilitation of sanitary sewer manholes completed. No scheduled construction activity.

    3. Sanitary Sewer Rehabilitation - Downtown Shattuck Area
      Shattuck Avenue, Addison Street
      Express Plumbing
      Project Notice and Map (.pdf)

      Work on the sanitary sewer main between Addison Street to Center Street on east side of Shattuck Square.

      Testing of the newly installed sanitary sewer main, laterals and manholes.

      Completed rehabilitation of the sanitary sewer main, laterals and manholes Sacramento Street (East side) between Rose and Cedar. Testing of 3 manholes remain.

      Completed repair of existing sanitary sewer main, manhole and laterals on Keith Avenue #1187 to #1202. Interior coating and testing of manhole remains to be done.

      rdbarrierNote: Businesses will continue to operate on their scheduled times. Businesses and Residents will be notified by contractor prior to working within the immediate areas. Please heed all “No Parking”, temporary directional signs in project area. Please DRIVE SLOW through the construction area. Pedestrians should be mindful of construction in sidewalk and crosswalk areas.

    4. Sanitary Sewer Rehabilitation
      Hopkins St., Peralta Ave., Monterey Ave., The Alameda and Backlines, Boynton Ave and backlines
      Andes Construction
      Project Notice and Maps (.pdf)

      Continue work on Hopkins Street from Peralta to Gilman (1200-1400 blocks) and from Colusa to Josephine (1700-1800 blocks). The work will involve the rehabilitation of the existing sanitary sewer mains, manholes and lower service laterals.

      Contractor will resume working in the easement areas between Milvia Street through Bonita Avenue to Martin Luther King Jr. Way (1200 block areas) and the easement areas of 512 Boynton and 21 Florida Avenue. Rehabilitation of the existing sewer main, laterals and manholes.

      rdbarrierNote: Residents will be notified by contractor prior to working within the immediate areas. Please heed all “No Parking”, temporary directional signs in project area. There will be an unusual loud noise during the insertion of the new sanitary sewer pipe into the existing pipe. During these events the contractor will try to muffle as much of the sound as possible. The replacement of the new sanitary sewer mains, laterals and manholes will occur during the working hours. Please DRIVE SLOW thru the construction area. Be aware of low tree branches along the road side.

  2. Storm Water Projects

    1. Claremont Creek Culvert Repair at Hazel Road
      56 and 75 Hazel Road
      Gold Wing Engineering, Inc.
      E-mail link to Project Engineer

      CCTV storm drain and sewer.

    2. FY 2015 Storm Drainage and Valley Gutter Improvement Project
      Bonita Ave/Berkeley Way, Fresno Ave/Sonoma Ave, Oregon St/Fulton St
      GradeTech, Inc.
      E-mail link to Project Engineer E-mail link to Project Inspector

      Punchlist work.

  3. Street Paving Projects

    1. Street Rehabilitation FY 2015
      Alcatraz Avenue, Channing Way, College Avenue, Durant Avenue, Dwight Way, Fulton Street, Hearst Avenue, and Sacramento Street
      MCK Services, Inc.
      Location Map (.pdf)  Project Notice (.pdf)

      No construction activity.

    2. FY 2015 Measure M Street Resurfacing and Reconstruction
      Various streets throughout Berkeley - See Project Notice or Location Map
      Gallagher & Burk, Inc.
      Location Map (.pdf)   Project Notice (.pdf)

      rdbarrierFull width grinding and finish-lift paving at:

      Addison St – Shattuck Ave and Oxford St
      Bancroft Way – Dana St and Telegraph Ave
      Buena Ave – McGee Ave and West end
      Comstock Ct – Cedar St and Jaynes St
      Glen Ave – Eunice St and Oak St
      Jaynes St – California St and Edith St
      Keeler Ave – Marin Ave and Grizzly Peak Blvd
      North St – Jaynes St and North end
      Parker St - MLK Jr Way and #1923 Parker St
      Terminal Pl – Addison St and North end
      Vine St – McGee Ave and Edith St

      Concrete work at:

      9th St – Dwight Way and Delaware St
      California St – Addison St and Dwight Way
      Various locations

      Adjustment of utilities at various locations.

      Striping layout at:

      10th St – Camelia St and North end
      Dwight Way – San Pablo Ave and Sacramento St
      Buena Ave – West end and McGee Ave
      Folger Ave – Hollis St and San Pablo Ave

    3. Potter Bay Bolivar Paving Project
      Potter Street, Bay Street, Bolivar Drive at south end of Aquatic Park
      GradeTech Inc.
      E-mail link to Project Inspector  E-mail link to Project Engineer

      rdbarrierWork on Bay Street. Please slow down through the construction area.

  4. Sidewalk & Pathway Repair Projects

    1. FY 2015 Proactive Sidewalk Project
      Various locations throughout the city
      AJW Construction
      E-mail link to Project Engineer  E-mail link to Project Inspector

      Weather permitting, sidewalk repair work at 1400-1700 blocks of Shattuck Avenue. After completion of Shattuck area, will move to 3100 block of Adeline.

  5. Other

    1. Flare Station Replacement and Well Field Upgrades
      11 Spinnaker Way, Cesar Chavez Park
      Innovative Construction Solutions
      E-mail link to Project Engineer   E-mail link to Project Inspector

      Well upgrades at locations throughout the park. Work includes excavating, backfill, and compaction.

  6. Outside Agencies' Projects

      State Route 13 Retaining Wall and Sidewalk Project
      Marcus Wagner, Caltrans Public Information Officer or (510) 322-8758
      CALTRANS Public Notice (.pdf)

      Starting July 13, 2015, CALTRANS will be removing a rock outcropping that interrupts access to the sidewalk adjacent to northbound State Route 13 and construct a standard sidewalk, adjacent roadway, and a retaining wall adjacent to the sidewalk on northbound State Route 13 (Tunnel Road) located between Hiller Drive and Vicente Road.

      rdbarrierMotorists should expect delays. All work is weather permitting. Access to the northbound sidewalk will be prohibited during construction.

    2. PGE
      E-mail link to City contact person

      Orchard Lane, Panoramic Way, Mosswood Road - Gas line replacement project - Orchard Lane complete. Start of work on Panoramic and Mosswood pending.

      Copper service replacements at various locations throughout the city.

      Install SCADA cabinet at:

      Mabel/Carrison - paving pending
      University/Curtis - paving pending
      900 Grayson
      1400 Virginia

      Restoration work and pole replacement work at various small locations throughout the city.

    3. EBMUD
      E-mail link to City contact person

      Dwight Way, Warring St, Derby St - Paving pending.

      rdbarrierHeinz Avenue from 7th Street to West end - Pipeline replacement.

      Folger at 7th - valve work scheduled for 11/30.

      Restoration work at numerous small areas throughout the city.

      Berkeley View Facility Upgrade
      SE corner of Shasta Road and Hill Road (next to Fire Station #7 on Shasta Road)
      EBMUD Community Affairs Office, (510) 287-0140,
      After hours, 1 (866) 403-2683
      EBMUD Public Notice (.pdf)
      EBMUD Public Notice - June 2015 Update (.pdf)

      Replacement of existing pumps, motors, electrical components and internal cranes. Contractor will be using the Shasta Reservoir property at the end of Bay Tree Lane for staging and parking. Construction is now scheduled to start in July 2015 and be completed in approximately 6 months.

      Ground Movement Pipeline Improvements on Euclid Ave between Cragmont and Keith

      For updated information and contacts regarding EBMUD Reservoir Replacement and Transmission Pipeline projects please follow the appropriate link below:

      Panoramic Hill Improvements

      Summit Reservoir Replacement Project (Spruce at Grizzly Peak)

      EBMUD Summit Reservoir Notice - December 2014 (.pdf)
      Summit Reservoir Update Notice - October 2015 (.pdf)

      Wildcat Pipeline Project

    4. AT&T Telephone
      E-mail link to City contact person

      Crews removing old poles throughout Berkeley.
      Investigative and cable pulling work within existing manholes and vaults throughout the city.

    5. University of California at Berkeley
      Information provided by
      UC contact person: Christine Shaff
      UC Berkeley Real Estate, (510) 643-4793

      UC Berkeley Art Museum and Pacific Film Archive
      Construction is underway for a project that will create a new home for BAM/PFA, a vibrant multi-media art center for the campus and community. This center is comprised of the re-purposed former UC printing plant at 2120 Oxford Street as well as new construction. The donor-funded facility will house BAM/PFA’s exhibition galleries, library, film study center; education and art-making spaces; store; cafe; and offices as well as a 230-seat theater and a 32-seat screening room. The new facility is scheduled to open January 31, 2016.

      For images of the new facility and more information about the new home for BAM/PFA please go to

      The Cal Aquatic Center
      A new intercollegiate aquatic facility located west of the University Health Service Tang Center at 2222 Bancroft Way. It will consist of three single level buildings surrounding a 52 meter swimming pool with dive tower. Construction is expected to be complete in summer 2016.

      Berkeley Way West
      Construction of a new academic building is scheduled to start in late December 2015 in the lot bounded by Berkeley Way, Shattuck Ave and Hearst Ave. The building will house the School of Public Health, School of Education, and Department of Psychology. Ground floor retail along is also planned. Construction is scheduled to continue through late 2018.

      Information about campus construction is available on the web at Questions or concerns can be addressed to Christine Shaff, UC Berkeley Real Estate, at (510) 643-4793 or Other campus resources include the UC Office of Environment Health and Safety at (510) 642-3073.


For information on Parks projects, please see the Parks Construction News page.

In all construction areas:

If you did not find the project you were looking for, it may have moved to the Recently Completed Projects page.

Recently completed sanitary sewer projects

Recently completed storm drain projects

Recently completed street rehabilitation projects

Recently completed sidewalk and pathway projects